The ground surface slopes 1 in 50 along a proposed railway embankment 150 m in length.

Question

The height of the embankment at zero chainage is 0.5 m, the width is 11 m and side slopes 2:1. If the falling gradient of the embankment is 1 in 150, the quantity of the earthwork calculated by Prismoidal formula, is____________________?

A. 3250 m3

B. 3225 m3

C. 3275 m3