a) Describe the typical steps used in a function point method to estimate the size of a software development project. 

Question

b) Describe the purpose and contents of a highlight report for presentation to the project board.

c) Monitoring progress has revealed that the project you are managing is not achieving its planned stage of progress. Describe the advantages and possible disadvantages of THREE control strategies you might consider using to get the project back on its planned level of progress.