If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively___________________?

Question

A. 3.5 and 5/6

B. 5 and 25/36

C. 3.5 and 25/36

D. 4 and 5/6