For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively,

Question

The expected time is__________________?

A. 8 days

B. 9 days

C. 10 days

D. 15 days

Leave an answer

Sorry, you do not have permission to answer to this question .